Share
A downtown Fresno redevelopment project six years in the making is seeking another extension.
Developers for the South Stadium Project are asking for one more year to negotiate a deal with the city for a building on Fulton Street. The Fresno City Council, acting as the Housing Successor to the Redevelopment Agency, will discuss at its regular meeting on Thursday.
The city received proposals for the now-$18 million project in 2014, choosing Noyan Frazier Capital, LLP, to redevelop portions of downtown Fresno. What was once a five-phase project is now down to just two along Fulton Street — an empty lot at the northwest corner of Fulton and Inyo streets and, three doors down, a vacant property known as the Berkeley’s Building that once housed a women’s clothing store.
The sale price from the city to Noyan Frazier Capital? One dollar per property.
Construction Dates Delayed
After the city awarded Noyan Frazier Capital its request for proposal, the two sides negotiated a deal known as a Disposition and Development Agreement on how the properties should be developed.
The first DDA, completed in 2016, covered Phase 1 of the project — a vacant lot at Fulton and Inyo called “The Park.” The plan remains a four-story mixed-use building for retail and affordable housing.
Construction was supposed to start by June 30, 2018. Various delays, mainly to secure state funding, pushed back those timelines. The current construction start date is by Nov. 20, 2020.
The project was estimated to cost $14 million, according to the 2016 DDA. It is now pegged at $18 million.
![Photo of the Berkeley's Building in Fresno, California](https://gvwire.s3.us-west-1.amazonaws.com/wp-content/uploads/2024/03/16164103/IMG_5864.jpg)
Extension Requested for Phase 4
The Phase 1 DDA allowed for Noyan Frazier Capital to negotiate exclusively for the Berkeley’s Building at 887 Fulton Street, identified as Phase 4. The property is owned by the Housing Successor — another level of government created years ago when then-Gov. Jerry Brown dissolved local redevelopment agencies.
Noyan Frazier Capital is asking the council to extend the negotiation period for a DDA of Phase 4 through April 11, 2021 (it is set to expire Saturday), with construction to start by Dec. 31, 2021.
This would be the third extension of the negotiation period. In return, Noyan Frazier Capital would pay a $5,000 fee.
In a letter to the city, Managing Partner Mehmet Noyan wrote that the Berkeley’s Building “is badly in need of remediation and structural repair. … I doubt that anyone has gone to the level of due diligence we have and understand what steps need to be taken to bring the building into an environmentally safe condition for occupancy.”
Noyan said that his company has spent more than $50,000 on the building’s preparations. He declined to talk to GV Wire for this story.
Three other phases of the project — phases 2 and 5 which would have redeveloped the old Gottschalks Building on Fulton, and Phase 3 which would have redeveloped a parking lot adjacent to Chukchansi Park — have been deleted.
Arias Wants Extensions Tied to Deadlines
City Council President Miguel Arias said another delay was to determine whether the Berkeley’s Building, which opened in 1961, was historic.
“There is no historical designation … (the options) are now to level it, start from scratch, or have a different use,” Arias said. “This extension would give them time to evaluate those options.”
Arias said he has been hesitant to extend other negotiations without meeting deadlines. Last month, he asked critical questions of another downtown DDA extension involving developer Cliff Tutelian.
“If the South Stadium project does not commence construction on time, this DDA would automatically terminate,” Arias said.
![Photo of an empty lot at Fulton and Inyo in downtown FresnoT](https://gvwire.s3.us-west-1.amazonaws.com/wp-content/uploads/2024/03/16164103/IMG_5858.jpg)
City Approved Funds Last Year after Frazier Filed Claim
Last year, the city council approved nearly $659,000 for the project to cover a shortfall in funding by a 4-1 vote.
Councilwoman Esmeralda Soria recused herself because she was in a romantic relationship with Frazier. The two are now engaged.
Councilman Garry Bredefeld voted no and later called for a revote because he said a key piece of information was missing — the fact that Frazier had filed a claim against the city.
Frazier filed the claim — initially for $10 million, but revised to more than $10,000 to conform with city filing standards — accusing the city of a biased audit against his nonprofit Central Valley Community Sports Foundation.
The city performed the audit looking into CVCSF’s subsidy to operate the Granite Park sports facility. The report said there were many bookkeeping irregularities, but no malfeasance.
Frazier denied wrongdoing and filed a claim as a prelude to possible legal action.
Arias said Frazier’s claim will have no bearing on his downtown project.
“These items are addressed on their own merits,” Arias said.
Arias said he could not provide an update on the status of Frazier’s claim.
Fresno Man Sentenced to 29 Years for Sexually Assaulting Children and Dog
13 hours ago
Bulldogs’ Two-Position Standout Tommy Hopfe Signs With Rockies
13 hours ago
Former Bulldog QB Jake Haener: I Have a ‘Rare Form of Skin Cancer’
14 hours ago
The Many Names of GOP Vice Presidential Nominee JD Vance
14 hours ago
Companies Cut Prices to Boost Sales, Consumers Respond
15 hours ago
What Italian Grandmothers Can Teach You About Healthy Eating
11 mins ago
Categories
![](https://gvwire.s3.us-west-1.amazonaws.com/wp-content/uploads/2024/07/25112306/AP2141106817163116-1-1024x576.jpg)
What Italian Grandmothers Can Teach You About Healthy Eating
![](https://gvwire.s3.us-west-1.amazonaws.com/wp-content/uploads/2024/07/26104129/021624-California-Forever-LE-CM-29.jpg-1024x576.jpg)
CA Has Seen Many New Towns, but This Big Project Is Stalled
![](https://gvwire.s3.us-west-1.amazonaws.com/wp-content/uploads/2024/07/26170645/Gage-Mason-20-was-sentenced-to-29-years-in-state-prison-for-sexually-assaulting-multiple-children-and-a-dog-and-will-also-be-required-to-register-as-a-sex-offender-1024x538.jpg)
Fresno Man Sentenced to 29 Years for Sexually Assaulting Children and Dog
![](https://gvwire.s3.us-west-1.amazonaws.com/wp-content/uploads/2024/07/26161707/Tommy-Hopfe-with-the-Colorado-Rockies_1280X720-1024x576.jpg)
Bulldogs’ Two-Position Standout Tommy Hopfe Signs With Rockies
![](https://gvwire.s3.us-west-1.amazonaws.com/wp-content/uploads/2024/07/26145457/image-2024-07-26T145350.189-1024x576.jpeg)