One of the state’s top bullet train contractors has sent a scorching 36-page letter to California high-speed rail officials, contradicting state claims that the line’s construction pace is on target and warning the project could miss a key 2022 federal deadline.
The letter, obtained by The Times, alleges that a multitude of problems have remained unresolved for years, including rapid turnover of state officials, continuing delays in obtaining land for the rail and the state’s failure to secure agreements with outside parties, including utilities and freight railroads. The delays will result in idled work sites and layoffs of field workers, says the letter, by construction giant Tutor Perini.
As of mid-November, construction teams can not build on more than 500 parcels in the Fresno area because the California High-Speed Rail Authority still lacks possession or proper documentation, according to the Jan. 4 letter. The company has completed all the work that could be done efficiently and as a result is now operating at other sites at a slower pace.
By Ralph Vartabedian | 12 Jan 2021
RELATED TOPICS:
Two Teens Charged in Shooting Death of Caleb Quick
1 day ago
Soviet-Era Spacecraft Plunges to Earth After 53 Years Stuck in Orbit
1 day ago
Tax the Rich? Slash Spending? Republicans Wrestle With Economic Priorities in the Trump Era
1 day ago
Experts Call Kennedy’s Plan to find Autism’s Cause Unrealistic
1 day ago
Trump’s Trip to Saudi Arabia Raises the Prospect of US Nuclear Cooperation With the Kingdom
1 day ago

US-China Tariff Talks to Continue Sunday, an Official Tells The Associated Press

Two Teens Charged in Shooting Death of Caleb Quick