The first day of classes at a new elementary school in southeast Fresno might have to be pushed back to August 2022 unless Fresno Unified School District soon advertises for bids on the $44 million project, a district administrator warns.
Listen to this article:

Such an agreement would guarantee that the project would use union labor and give bargaining rights to all involved unions for setting wage rates and benefits. The district would need to negotiate the agreement before the project is put out to bid.
Proponents of PLAs say such agreements help ensure that projects finish on time, while opponents say they result in higher costs.
Timeline Scheduled August 2021 Opening
According to the original timeline, the project was supposed to be advertised Sept. 11, with a bid opening Oct. 2 and project award Nov. 6, Temple said.
“The schedule plans for substantial project completion in late May 2021 to provide adequate time to furnish and stock the new school for a smooth August 2021 opening to staff and students,” Temple wrote. “This schedule is tight but achievable, if it stays on track.”
The project schedule was timed to take advantage of off-peak market conditions and allow the contractor sufficient time to order materials such as structural steel, she said.
If the advertisement is delayed by even four weeks from Sept. 11, the school’s opening would have to be pushed back to August 2022, and the project costs could grow because of rising costs in the construction industry, Temple warned.
The item is not on Wednesday’s School Board agenda.
Former U.S. Poet Laureate Is School’s Namesake
The school, named for former U.S. poet laureate and Fowler native Juan Felipe Herrera, will be built on a site now occupied by Phoenix Secondary Academy on East Church Avenue between Willow and Peach avenues. Phoenix Secondary is moving to a new site further east on Church Avenue at Orangewood Avenue.
The district plans for the school to have a science, technology, engineering, arts, and mathematics (STEAM) theme. District staff in charge of developing the school are scheduled this month to visit elementary schools identified by the California Department of Education as having effective STEAM programs.
The school is the only new elementary on Fresno Unified’s Measure X priority projects list.
Measure X is a $225 million ballot measure approved by voters in November 2016.
Pentagon Directs Military to Pull Library Books That Address Diversity, Anti-Racism, Gender Issues
33 minutes ago
Fresno Pays the Most for Electricity. What Are Lawmakers Doing About It?
34 minutes ago
US to Accept White South African Refugees While Other Programs Remain Paused
42 minutes ago
Leo XIV’s Service to Poor Propelled Him to Papacy, Cardinals Say
1 hour ago
The State Law Taking a Financial Toll on California Budgets
1 hour ago
Iran to Send Russia Launchers for Short-Range Missiles, Sources Say
1 hour ago
Fresno Police Officer Arrested on Sexual Battery Charges
18 minutes ago
Categories

Fresno Police Officer Arrested on Sexual Battery Charges

Mayor Baraka of Newark, New Jersey, Arrested at ICE Detention Center He Has Been Protesting

FDA Will Allow Three New Color Additives Made From Minerals, Algae and Flower Petals

Pentagon Directs Military to Pull Library Books That Address Diversity, Anti-Racism, Gender Issues

Fresno Pays the Most for Electricity. What Are Lawmakers Doing About It?

US to Accept White South African Refugees While Other Programs Remain Paused